P272 is now entering it’s final stage.

150 150 David

P272 is now entering it’s final stage.

By 1st April all MD supplies with AMR meters must be converted to HH.

While OFGEM intends to take action against failing suppliers, it does recognize that some new contracts will be within their initial 45 day period before the change can take place.

Any MD contract now quoted as HH will require a MOP contract charged by one supplier as £265 per annum on a 5-year contract.
However this relative small charge may be more than compensated by a much lower standing charge as long a no capacity charges are being added.